An unnamed hyperscaler put $200 million up front for 600 MW at Fermi's Amarillo campus, and no lease is signed, while the 650 MW TensorWave deal is dead. We count power interest, not a tenant.
AirTrunk took exclusivity on 260 MW of solar, an 800 MWh battery, and up to 350 MW of wind in New South Wales, for 2030 to 2032. We file it as offtake intent, not operating power.
EverWind's Point Tupper service is interruptible on 10 minutes' notice, and the company takes incremental grid costs of $74 million or more, pending board approval. We watch whether that tariff holds.
Sabey signed a 10-year virtual deal for 43.5 MW from an operating Pecos County solar farm, about 130 GWh a year. We do not treat a virtual contract as power delivered at the meter.
ERock says work has started on a 366 MW gas plant for Meta's El Paso campus, aimed at mid-2027, and plans 2.1 GW a year of factory capacity by 2028. We log the plant as under construction.
New Era says up to 207 MW is under a 20-year deal for its Ector County first phase, aimed at the third quarter of 2027. We note the lease is still nonbinding and 99 more acres are under contract.
Nscale's new prospectus shows 50,000 GPUs live, double the August figure, and Anthropic opted into a second West Virginia building. We still treat that building as unsigned.
Rowan added $1.5 billion of corporate credit and says 1.2 GW is already contracted across Texas, Maryland, and Oregon. We treat the new facilities as dry powder, not new leases.
Insite DC filed four buildings on a truck yard in Tarneit, near Melbourne, and points to 100 MW across six sites. We see a planning file, with no tenant or power deal disclosed.
Nebius signed $12 billion of third-quarter contracts with customers prepaying the build. A Microsoft hall in New Jersey slipped after temporary power was pulled. We note it was not canceled.
CDC refiled a Sydney campus as six buildings totaling 1.4 GW, up from one 144 MW building. We count an application, not an approval, and we do not book it as contracted load.
AWS opened its Chile region to select customers, with general availability due by year end and $4 billion planned. We count a region as live only once it is generally available.
Iroquois asked FERC to extend its New York and Connecticut compression project to March 25, 2029, with Brookfield still short of a state permit. We mark the request as pending. Comments close Nov. 24.
RBN cut its five-year Texas gas-demand growth view to 1 Bcf a day, down 0.4, after the governor's race, and said off-grid sites burn about twice the gas. We do not treat queues as load.
The gas association cites a Nov. 7 LNG feedgas record of 20.3 Bcf a day and an EIA winter Henry Hub forecast of $2.87, 16 percent under last month. We watch fuel cost for gas-fired sites.
Westlake voted unanimously to allow a 1.1 million square foot data center beside Keller after a noise and fire deal. We mark the local permit as granted and the tenant as undisclosed.
Kansas City unanimously denied a 20-story data center at 934 Central. Sen. Hawley wants a federal pause until rate protections pass. We treat the local project as dead and the federal idea as talk.
Waterville rezoned 48 port acres to light industrial and accepted petitions for a charter ban on data centers. The port says the site is too close to houses. We do not treat the ban as on the ballot.
Massachusetts organizers want a 2028 ballot rule: a two-thirds local vote and full renewable supply above 5 MW. We note signatures are aimed at next fall, so nothing is on a ballot yet.
Minneapolis passed data center rules 7-6, limited to existing downtown buildings and not as the main use. A ban failed. We note the mayor still has to sign, and the pause ends Nov. 21.
Oklahoma City extended its pause on data centers above 75 MW through 2027, and Edmond extended a full pause through June 2027. We add both to the list of cities not taking new permits.
Residents sued OpenAI and Effingham County over the 3.2 GW, $30 billion Project Camellia, saying it advanced out of public view. We note a board vote moved to Nov. 19 and the case has not been heard.
Indiantown gave a first reading to a one-year data center pause that exempts projects already in line, including a 606-acre site. We mark it as a first reading, with a second vote set for Nov. 19.