SpaceX put about $50 billion on its Cochise County campus and more than $24 billion on Starbase, both facing Dec. 9 hearings. We count both as proposed until the county permit and tax abatement votes.
Dominion has 12.2 GW of data center load under final service agreements out of about 54.9 GW in its pipeline, about 22 percent. We weight signed agreements over engineering letters in sizing a market.
Constellation signed a 20-year, 270 MW Peak+ deal starting in 2028 that bundles existing nuclear output with new capacity. Buyer and region undisclosed, so we log the structure and hold the location.
BloombergNEF counts 181 GW of on-site gas capacity proposed at data centers in the US, UK and Europe, with 90 percent planned in the US. We read it as a measure of how long grid connections now take.
QLEVR won a special use permit for a 90,000 square foot, 16 MW facility in Rossford, Ohio, with a private substation and a $150 million budget. A final site plan is still due. Preliminary approval.
Canada's assessment agency said construction on Meta's 1 GW Sturgeon County campus had substantially begun, so it cannot be designated for federal review. Under construction, with its own gas plant.
Equitrans filed a 4.9-mile, 108 MMcf a day lateral to feed the 625 MW Wolf Summit plant in West Virginia under its blanket certificate. Authorized automatically unless a protest stands, so pending.
The comment period on FERC's draft review of Cheniere's Corpus Christi Stage 4 closed Nov. 9. The plan adds about 25.8 miles of 42-inch pipe and four trains, and it is not approved.
December gas traded at $3.306 per MMBtu late Thursday, up 2.83 percent, with output at a nine-month low of 110.9 Bcf a day and storage 54 Bcf above the five-year average. We watch fuel cost.
The 444.45-acre Starbase site was de-annexed from Brownsville this summer for $220 million in water funding, which put it outside the city's new 90-day moratorium. Note jurisdiction as a siting lever.
Amazon paid $72 million for 13 acres off Hazel Park Court in Chantilly, where it could build data centers by right. We count it as a closed land purchase.
Saline Township reaffirmed a 50 percent, 12-year tax break for Oracle at The Barn on Nov. 11. State Tax Commission approval is still required, so the incentive stays pending.
Stanton, Tennessee heard an annexation request for about 164 acres that residents tie to a possible data center, with a vote expected next week. No user is confirmed, so we treat it as speculative.
Florida's PSC voted 5-0 to deny Duke Energy Florida's large-load tariff under the state's 50 MW full-cost law, with leave to refile and no date set. Expect more states to test tariffs this strictly.
The Senate substitute would make every data center, with no size floor, pay its full grid and transmission costs, with a final vote possible the week of Nov. 16. Nothing has passed. Pending.
Boise paused applications for data centers over 100,000 square feet or 20 MW for six months, with an option for a 12-month interim rule. We add it to the list of metros closed to new filings for now.
Riverside, California voted 5-2 for a 45-day moratorium on new or expanded data centers that can be extended 22.5 months. No commercial project is proposed there, so the effect is on future siting.
SpaceX filed a 6 GW, nine-building campus on 747 acres served by two Arizona co-ops, about $3.6 billion in grid upgrades and a county hearing Dec. 9. Proposed until the hearing and power plan settle.
Invitium agreed nonbinding terms for about 2 GW of gas, fuel cell, and battery supply to a QTS project. PPL's Pennsylvania pipeline is 35.3 GW, 8.5 GW under construction. Pending a signed contract.
NRG expects definitive agreements by year end for a 1.2 GW combined-cycle plant serving about 1 GW of data center load, with operation in late 2029. We mark it planned until the deal is signed.
APS asked Arizona regulators to approve a 25-year subscription contract for TSMC, about 1.9 GW at full buildout, tied to its proposed Desert Sun gas plant. We see a template for large-load tariffs.
Quantum DC paused a 1,200 MW campus in Tungkillo, South Australia after local protests, and a Sydney proposal was dropped over the weekend. We read it as the same consent problem developers face here.
Starbase posted a hearing notice for a $24 billion gas plant and computing site, with a vote set for December. We count it as proposed and watch how the incoming governor treats new permits.
Amazon confirmed a Glen Rose campus with about 550 jobs, and an earlier abatement filing described up to 18 buildings on 435 acres. We log the confirmation and hold the size until Amazon states it.
Microsoft says its Johor Bahru region will become its largest in Southeast Asia, with closed-loop cooling and no opening date set. We do not count capacity until it opens.
December gas rose 2 percent to $3.353 per MMBtu, a nine-month high, on colder forecasts and near-record LNG feedgas, while output slipped to 112.3 bcfd. We watch fuel cost for gas-backed sites.
FERC set an environmental review schedule for 183,100 Dth/d of eastbound Marcellus capacity, with NJNG anchoring 175,000 Dth/d and a Dec. 1, 2027 target. We mark it in review, not approved.
Eastern Shore Natural Gas filed a $75 million expansion starting with a 2.55-mile, 24-inch loop, with all new capacity under 20-year contracts. We keep it pending FERC approval.
Energy Transfer's final investment decision: a 215-mile, 1.2 Bcf a day line from northeast Louisiana to Florida Gas, targeting March 2030. Sanctioned; final sizing after open season closes Nov. 25.
The Southeast Connector would carry at least 2.6 Bcf a day through about 150 Tennessee miles, with FERC pre-filing by year end and phased service by late 2030. We treat the route as unsettled.
AWS confirmed it bought nearly 1,000 acres in West Richland, Washington, after a $263.7 million resale, with three buildings first and up to 21. No site plan is filed, so we keep it unpermitted.
Residents sued McCormick County, South Carolina, over a September rezoning for a 678-acre data center, alleging notice and procedure failures. We flag the site as contested until the court rules.
Australia's rule maker set a 30 MW threshold and ride-through standards for large data center loads, effective now with a 6-month grace period. Same direction as large-load rules being filed here.
Malaysia will require operators to disclose power use and GPU imports, and says 55 of 117 approved projects operate. Unused booked capacity will still be billed. Similar pressure on reservations here.